Timescale of project
| Leaflet drop | Mid September |
| Consultation | September/ October 2005 |
| Project plan in place | October 2005 |
| Planning permission | November 2005 |
| Planning application result | Mid February 2006 |
| Working drawings | March- May 2006 |
| Building regulations | May-June 2006 |
| Bill of quantities | June 2006 |
| Tenders | July 2006 |
| Tender appraisal & approval | August 2006 |
| Construction phase 1. | September 2006 – February 2007 |
| Construction phase 2. | March-April 2007 |
| Completion | May 2007 |